- CO2 arrangement plan.
- Procedure of firing.
- Number of bottles designated for each place protected.
- Number of non return valves.
After releasing:
- Always advisable to wait before carrying out an investigation.
- Maintain boundary cooling and observe temperature at various levels.
- Once a distinct fall in temperature has been observed an internal inspection and assessment may be carried out.
- Breathing apparagraphtus to be donned when entering the space. Checks on breathing apparagraphtus. 2/e and oiler to enter.
- Inspection to be carried out with spray fire fighting equipment, safety line and communication checked prior to entry.
- Once it has been confirmed that fire has been brought under control an additional assessment by chief engineer.
- When both opinions agreed upon damage control party to be sent in for cooling down work.