Person in charge of the work team …………………………………………………………
Section 3 |
||
The work has been completed and all persons under my supervision, material and equipment have been withdrawn. | ||
Authorised person in charge ……………………………… | Time…………… | Date……………… |
First Copy for display at work area.
Second copy for Ship’s records
NOTES
Tests for combustible gas should be carried out immediately before commencement of hot work and at frequent intervals as long as the work is in progress.
General:
- Starting / finishing time must not exceed the Masters/ Responsible Officer’s working hours. A fresh permit must be issued thereafter.
- Specific location of hot work to be given.
- Description of work to include type of equipment to be used.
Section 1
Applies to all hazardous work not involving naked flame or continuous spark production, and would include use of electrical equipment, use of air driven rotary equipment, hammering or mechanical chipping and movement/ lifting equipment or materials over or near operating plant
Section 2
Applies to all hot work involving high temperatures, open flames, electric arc or continuous source of spark etc. This type of work includes but is not limited to welding, burning, grinding, sand or grit blasting, and metal chipping.
Section 3
Permit to be closed out by Responsible officer upon completion of work.